How to Operate a Crane: 21 Story 6 Days To Build A Floor
rotyag rotyag
3.11K subscribers
7,559 views
53

 Published On Mar 15, 2015

This has to be played full screen to make any sense. It's a one week time lapse of the 60+ hours it takes to build a floor on a high-rise. We poured the floor and vertical all in one day (thur). By that afternoon we were stocking shoring for the next deck. Strip the vertical Friday and jump the walls and concrete placing boom. Saturday jump tables and Monday stock rebar. and feed the deck machine for the next few days all while breaking to hang wall/window panels with the crane on the outside of the building.

I love production operation like this. 15-17 lift cycles per hour. The day goes quick. My only personal pet-peeve is that some contractors don't afford breaks to the operator. 12 hours 6 days a week and no breaks.